Delivery Timeline

Milstones from WNDC's Delivery Timeline 2004 - 2014

View Year
  • 2004
  • 2005
  • 2006
  • 2007
  • 2008
  • 2009
  • 2010
  • 2011
  • 2012
  • 2013
  • 2014
Close List
2004
December

2004

WNDC was established by the Government
2005
2006
April

2006

WNDC planning service
established
July

2006

Royal & Derngate
theatre re-opens
November

2006

Edgar Mobbs Way
opened
2007
July

2007

78 Derngate visitor
centre opens
December

2007

Planning service has over 25,000 homes in live applications
2008
July

2008

Upton flood
defences completed
September

2008

King's Park conference
centre extended
October

2008

Stronger Communities Fund launched
December

2008

Upton Valley Way
North opened
2009
February

2009

Portfolio Innovation Centre
expanded
February

2009

Construction Futures officially launched
March

2009

Abbey Retail Park
opened
April

2009

Planning service completes first 'standard charge' agreement
May

2009

Brackmills CCTV
completed
June

2009

Northampton Greenways
completed
July

2009

Northampton public realm improvements completed
October

2009

Southern section of Sandy Lane Relief Road completed
2010
Market Square
January

2010

Market Square improvements completed
January

2010

Upton Lodge Farm House
completed
April

2010

Bury Mount and Watermeadows opened
2011
January

2011

Sandy Lane Improvements North opened
May

2011

iCon Innovation Centre
opened
November

2011

London Rd/Ransome Rd junction improvements completed
2012
January

2012

Avon Nunn Mills Compulsory Purchase Order submitted
March

2012

Northampton Marina
opened
March

2012

Moat Lane Development Partner announced
April

2012

Carlsberg Enterprise Zone development starts
April

2012

Extension to Watermeadows
opened
April

2012

Planning powers transferred to the local authorities
May

2012

Northampton Railway Station
funding confirmed
May

2012

St Peter's Waterside Compulsory Purchase Order submitted
July

2012

St John's University accomodation development starts
October

2012

Construction of Northampton
Bus Station starts
November

2012

Deal agreed for redevelopment of Avon Nunn Mills
December

2012

NN Contemporary Art Gallery officially opened

2012

County Council Cabinet approves Project Angel development
2013
April

2013

St Peter's Waterside land acquisitions complete
May

2013

Avon Nunn Mills
CPO approved
June

2013

Construction of Northampton
Railway Station starts
October

2013

WNDC transfers ownership of
Construction Futures
October

2013

Disused Railway line running through Avon Nunn Mills is acquired
December

2013

Construction of largest phase of Moat Lane starts
December

2013

Errol Flynn Filmhouse
opens
December

2013

St Peter's Waterside
Innovation Centre work starts
December

2013

Kier Property confirmed as
St Peter's Waterside developer
December

2013

Planning committee approval
for University of
Northampton Campus
2014
January

2014

Northampton Bus Station
opens
March

2014

Demolition works completed at St Peter's Waterside
March

2014

WNDC closes, after completing its delivery plan.